A master facility plan ensures an environmentally sustainable campus that meets current and future learning needs

 


2020-2021

  • There is no evidence.

2021-2022

  • Flansburgh redesigned our Master Plan.

2022-2023

  • Phase 0 completed: cafeteria and pool.
  • Project Manager position was hired and onboarded.
  • Architectural firm was selected.
  • Feasibility assessment of aquatic center.

2023-2024

  • Final ES building design.
  • Stage 1 building approval through municipality.
  • Construction company bidding process.

2024-2025

  • Internal agreement on construction company.
  • Prepared to present stage 2 to municipality.